Shraddha Landmark Private Limited

Deedo IDDD-3H0E

Of 7 registrations whose promised date has arrived, 3 kept it (43%). The rest ran a median 4 mo late.

Projects1515 RERA registrations
Kept RERA date43%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

12 of 15 registrations with dates moved or missed their RERA date · months late against the original promise

15 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shraddha PrideP51800024932KurlaCertificate Signed30 Dec 202430 Dec 2024On date
Shraddha ParamountP51800024933KurlaCertificate Signed30 Dec 202430 Dec 2024On date
Shraddha PassionP51800027842KurlaCertificate Signed30 Jun 202430 Jun 2024On date
Shraddha ClassicP51800028400KanjurmargCertificate Signed30 Jun 202730 Oct 2027+4 mo
Shraddha VardaanP51800028936KurlaCertificate Signed31 Dec 202730 Apr 2028+4 mo
Shraddha PrivilegeP51800033921KurlaCertificate Signed31 Dec 202531 Dec 2025+11 mo*
Shraddha PearlP51800046124KurlaCertificate Signed31 Dec 202531 Dec 2025+11 mo*
Shraddha ProminentP51800046232KurlaCertificate Signed31 Dec 202630 Apr 2027+4 mo
Shraddha PanacheP51800046277KurlaCertificate Signed31 Dec 202531 Dec 2025+11 mo*
Shraddha PresidencyP51800050356HariyaliCertificate Signed31 Dec 202630 Apr 2027+4 mo
Shivmangal ResidencyP51800051741BhandupCertificate Signed31 Aug 202631 Dec 2026+4 mo
Shraddha ImperiaP51800054815KanjurmargCertificate Signed31 May 202830 Sep 2028+4 mo
Bhandup Siddhivinayak CHS LtdP51800056282BhandupCertificate Signed30 Jun 202830 Oct 2028+4 mo
Vanita Sadan CHSP51800077422BhandupCertificate Signed31 Dec 202830 Apr 2029+4 mo
Shraddha Vardaan PlazaP51800077626KanjurmargCertificate Signed31 Aug 202931 Dec 2029+4 mo
Show all 15 registrationsShow fewer

Shraddha Landmark Private Limited, in questions

Does Shraddha Landmark Private Limited finish projects on time?

Of 7 MahaRERA registrations whose promised completion date has arrived, 3 kept it (43%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shraddha Landmark Private Limited registered with MahaRERA?

15 projects under 15 MahaRERA registrations; 3 completed on MahaRERA.

Does Shraddha Landmark Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology