Shore Dwellings Private Limited
Deedo IDDD-895NOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 76 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mantri EmporioP52100005228 | Pune (M Corp.) | Certificate Signed | 31 Jan 2020 | 31 Mar 2026 | +81 mo* |
| Mantri VantageP52100008390 | Kharadi | Certificate Signed | 30 Dec 2020 | 29 Apr 2022 | +70 mo* |
Shore Dwellings Private Limited, in questions
Does Shore Dwellings Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 76 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shore Dwellings Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Shore Dwellings Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.