Shoden Developers Private Limited
Deedo IDDD-E657None of 4 registrations has reached its promised completion date yet.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hiranandani Westgate Phase 1P51700077268 | Thane (M Corp.) | Certificate Signed | 31 Oct 2031 | 29 Feb 2032 | +4 mo |
| Hiranandani Westgate - HampsteadPR1331012503026 | Kavesar | Certificate Signed | 30 Apr 2033 | 30 Apr 2033 | On date |
| Hiranandani Maitri Park Phase 1PR1180002600200 | Chembur | Certificate Signed | 31 Mar 2031 | 31 Jul 2031 | +4 mo |
| Hiranandani BluecrestPR1180002602042 | Borivali | Certificate Signed | 31 Aug 2033 | 31 Aug 2033 | On date |
Shoden Developers Private Limited, in questions
Does Shoden Developers Private Limited finish projects on time?
None of its 4 MahaRERA registrations has reached its promised completion date yet.
How many projects has Shoden Developers Private Limited registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Shoden Developers Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.