Company or firm · first RERA registration 2017

Shivshahi Punarvasan Prakalp Ltd

Deedo IDDD-47WH

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 34 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay34 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
S R Scheme At Turbhe Mandale MankhurdP51800003471KurlaCertificate Signed30 Dec 202330 Dec 2023+34 mo*
S R Scheme At Rahul Nagar, SewreeP51900005130Ward FsouthCertificate Signed30 Dec 202330 Dec 2023On date

Shivshahi Punarvasan Prakalp Ltd, in questions

Does Shivshahi Punarvasan Prakalp Ltd finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 34 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shivshahi Punarvasan Prakalp Ltd registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Shivshahi Punarvasan Prakalp Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology