Shivling Vasant Jare

Deedo IDDD-47ZC

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 55 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay55 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai VillaP52100018962Pimpri Chinchawad (M Corp.)Certificate Signed31 Mar 202130 Jun 2024+68 mo*
Sai LeelaP52100027724ChikhaliCertificate Signed30 Jun 202330 Jun 2023+41 mo*

Shivling Vasant Jare, in questions

Does Shivling Vasant Jare finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 55 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shivling Vasant Jare registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Shivling Vasant Jare have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology