Shivam Lifestyle
Deedo IDDD-FZ8HOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Suprabha-Shivam LifestyleP51800029652 | Kurla | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Shivam ClassicP51800056058 | Chembur | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
| Shivam SunviewP51800080339 | Chembur | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Shivam Lifestyle, in questions
Does Shivam Lifestyle finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shivam Lifestyle registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Shivam Lifestyle have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.