Company or firm · first RERA registration 2017

Shiv Shakti Developers

Deedo IDDD-A3MD

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shakti ResidencyP52000010973DerawaliCertificate Signed30 Oct 201830 Oct 2020+24 mo
Shiv Shakti ComplexP52000048777ChikhaleCertificate Signed31 Dec 202831 Dec 2028On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology