Company or firm · first RERA registration 2017
Shiv Shakti Developers
Deedo IDDD-A3MDOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shakti ResidencyP52000010973 | Derawali | Certificate Signed | 30 Oct 2018 | 30 Oct 2020 | +24 mo |
| Shiv Shakti ComplexP52000048777 | Chikhale | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology