Shiv Sabari Developers
Deedo IDDD-NHC1Of 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sabari Sangam Wing AP51800001271 | Kurla | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
Shiv Sabari Developers, in questions
Does Shiv Sabari Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shiv Sabari Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Shiv Sabari Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.