Shiv Properties

Deedo IDDD-C7AK

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 28 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay28 mowhen late
Flats sold, all time2registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
North East Business CornerP52100027249Pimpri Chinchawad (M Corp.)Certificate Signed30 Jun 202430 Jun 2024+28 mo*
North East Business CapitalP52100028718Pimpri Chinchawad (M Corp.)Certificate Signed30 Jun 202430 Jun 2024+28 mo*
North East Business CentreP52100047204ChikhaliCertificate Signed30 Nov 202630 Mar 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology