Company or firm · first RERA registration 2020
Shiv Properties
Deedo IDDD-C7AKOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 28 mo late.
Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay28 mowhen late
Flats sold, all time2registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| North East Business CornerP52100027249 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +28 mo* |
| North East Business CapitalP52100028718 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +28 mo* |
| North East Business CentreP52100047204 | Chikhali | Certificate Signed | 30 Nov 2026 | 30 Mar 2027 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology