Sheth Developers Private Limited
Deedo IDDD-5DAVOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 36 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Sheth Cnergy Ph 1 - Upto 11th FloorRegulatory order: PROJECT NAME: SHETH CNERGY PH 1 - UPTO 11TH FLOOR (Regulatory Case No. 342 OF 2025) dated 12 March, 2025. | 12 Mar 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sheth Cnergy Ph 1 - Upto 11th FloorP51700023047 | Thane (M Corp.) | Certificate Signed | 29 Dec 2024 | 28 Dec 2027 | +36 mo |
Sheth Developers Private Limited, in questions
Does Sheth Developers Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 36 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sheth Developers Private Limited registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Sheth Developers Private Limited have MahaRERA regulatory cases?
1 regulatory case name its registrations.