Skip to content
Company or firm · first RERA registration 2023

Sethi Realtors

Deedo IDDD-282G

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sethi PalacioP99000053620Vasai Virar City (M Corp)Certificate Signed31 Dec 202830 Apr 2029+4 mo
Sethi Palacio B And C WingP99000080853Vasai Virar City (M Corp)Certificate Signed30 Apr 202930 Aug 2029+4 mo

Sethi Realtors, in questions

Does Sethi Realtors finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Sethi Realtors registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Sethi Realtors have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology