Sealink Construction Co. Pvt. Ltd
Deedo IDDD-G9Y4Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 22 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mittal Enclave Mittal Centre ShoppingP99000005104 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Mittal Enclave Gokul Sector Bldg No 4P99000006573 | Vasai Virar City (M Corp) | Certificate Signed | 31 Dec 2018 | 30 Oct 2020 | +22 mo |
| Mittal Enclave Bldg no 3 Wing CDEP99000008509 | Vasai | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Mittal Enclave Mittal Centre ShoppingP99000008632 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Mittal EnclaveP99000012403 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
Sealink Construction Co. Pvt. Ltd, in questions
Does Sealink Construction Co. Pvt. Ltd finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 4 kept it (80%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sealink Construction Co. Pvt. Ltd registered with MahaRERA?
4 projects under 5 MahaRERA registrations; 5 completed on MahaRERA.
Does Sealink Construction Co. Pvt. Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.