Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 33 mo — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay33 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases4includes insolvency
Schema Enterprises Private Limited developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Tropical EliteP51700006657Thane (M Corp.)Certificate Signed31 May 201830 Dec 2022+55 mo
Tropical EliteP51700018220Thane (M Corp.)Certificate Signed30 Dec 202130 Nov 2022+11 mo