Company or firm · first RERA registration 2017
Schema Enterprises Private Limited
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 33 mo — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay33 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases4includes insolvency
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Tropical EliteRegulatory order: PROJECT NAME: TROPICAL ELITE PHASE 2 (Regulatory Case No.30 of 2023) dated 13 July 2023. | 31 Jul 2023 |
| Regulatory order | Tropical EliteRegulatory order: PROJECT NAME: TROPICAL ELITE (Regulatory Case No. 28 of 2023) dated 13 July 2023. | 31 Jul 2023 |
| Listed as an NCLT insolvency project | Tropical EliteListed as NCLT project: TROPICAL ELITE PHASE 2 | Not on record |
| Listed as an NCLT insolvency project | Tropical EliteListed as NCLT project: TROPICAL ELITE | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tropical EliteP51700006657 | Thane (M Corp.) | Certificate Signed | 31 May 2018 | 30 Dec 2022 | +55 mo |
| Tropical EliteP51700018220 | Thane (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Nov 2022 | +11 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology