Sarthak Buildcon
Deedo IDDD-034GOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sarthak HomesP52000027372 | Karanjade | Certificate Signed | 30 Jun 2023 | 29 Jun 2024 | +12 mo |
| Sarthak NanoP52000027380 | Karanjade | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
Sarthak Buildcon, in questions
Does Sarthak Buildcon finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sarthak Buildcon registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Sarthak Buildcon have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
