Saptrishi Realtors
Deedo IDDD-RXWEOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 100 mo late.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Saptarshi HeightsP51800010738 | Borivali | Certificate Signed | 31 Jul 2018 | 31 Jan 2021 | +100 mo* |
| Saptarshi MarkP51800017508 | Kurla | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Saptarshi AvalonP51800021280 | Kurla | Certificate Signed | 30 Apr 2027 | 30 Apr 2027 | On date |
Saptrishi Realtors, in questions
Does Saptrishi Realtors finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 100 mo late. Across Maharashtra, 73% kept their date.
How many projects has Saptrishi Realtors registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Saptrishi Realtors have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.