Deedo IDDD-1Q8BOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 31 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Crystal CornerP52100004065 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Mar 2018 | 30 Oct 2020 | +31 mo |
Saptgiri Developers, in questions
Does Saptgiri Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 31 mo late. Across Maharashtra, 73% kept their date.
How many projects has Saptgiri Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Saptgiri Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.