Deedo IDDD-SDTQOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Srikara AvenueP52000046836 | Koyana Velhe | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Aakshay CornerPM1270002400051 | Taloje Panchnad | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Santosh Ramashish Pandey, in questions
Does Santosh Ramashish Pandey finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Santosh Ramashish Pandey registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Santosh Ramashish Pandey have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.