Sandesh Jivanlal Kakkad
Deedo IDDD-E63EOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 38 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gurukrupa PlazaP51400023751 | Jalna (M Cl) | Certificate Signed | 30 May 2023 | 30 May 2023 | +42 mo* |
| Gurukrupa ApartmentP51400034609 | Jalna (M Cl) | Certificate Signed | 31 Jan 2024 | 31 Jan 2024 | +34 mo* |
Sandesh Jivanlal Kakkad, in questions
Does Sandesh Jivanlal Kakkad finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 38 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sandesh Jivanlal Kakkad registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sandesh Jivanlal Kakkad have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.