Skip to content
Company or firm · first RERA registration 2017

Sandesh Chandrakant Kamat

Deedo IDDD-GHTB

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Brahmand ResidencyP51800006539Vengurla (M Cl)Certificate Signed27 Dec 202627 Dec 2026On date

Sandesh Chandrakant Kamat, in questions

Does Sandesh Chandrakant Kamat finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Sandesh Chandrakant Kamat registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sandesh Chandrakant Kamat have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology