Individual promoter · first RERA registration 2021

Sandeep Sambhaji Godase

Deedo IDDD-BRM6

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay48 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dwarka HouseP52100030712Alandi (M Cl)Certificate Signed30 Nov 202230 Nov 2022+48 mo*

Sandeep Sambhaji Godase, in questions

Does Sandeep Sambhaji Godase finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sandeep Sambhaji Godase registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sandeep Sambhaji Godase have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology