Sandeep Dwellers Pvt. Ltd
Deedo IDDD-64BBOf 14 registrations whose promised date has arrived, 11 kept it (79%). The rest ran a median 4 mo late.
Delivery record
14 of 28 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 28 registrations
28 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | SDPL Greens IIDeregistered: SDPL Greens II | Not on record |
| Deregistered | SDPL ParadiseDeregistered: Sdpl Paradise - Iii | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SDPL ParadiseP50500006021 | Nagpur (M Corp.) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| SDPL Aashray - IP50500006120 | Nagpur (M Corp.) | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| SDPL Greens IIP50500007483 | Wanjara | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| SDPL Aashray WanjaraP50500013707 | Wanjara | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| SDPL Aashray DabhaP50500014329 | Nagpur (M Corp.) | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| SDPL RoyaleP50500016581 | Nagpur (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| SDPL Aashray WanjaraP50500018042 | Wanjara | Certificate Signed | 29 Dec 2027 | 29 Apr 2028 | +4 mo |
| SDPL ArihantP50500019230 | Nagpur (M Corp.) | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| SPDL Greens Row House Phase IP50500022603 | Wanjara | Completed | 28 Aug 2025 | — | On date |
| SDPL Aashray BeltarodiP50500023552 | Beltarodi | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| SDPL ParadiseP50500026440 | Nagpur (M Corp.) | Certificate Signed | 30 Mar 2026 | 30 Mar 2026 | +8 mo* |
| SDPL Aashray HazaripahadP50500026715 | Nagpur (M Corp.) | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| SDPL OmP50500026827 | Nagpur (M Corp.) | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| SDPL Aashray GodhaniP50500030259 | Godhani (Railway) | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| SDPL Aashray DabhaP50500033667 | Nagpur (M Corp.) | Certificate Signed | 31 Jan 2027 | 31 May 2027 | +4 mo |
| SDPL Aashray HazaripahadP50500034184 | Nagpur (M Corp.) | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| SDPL Aashray HazaripahadP50500034209 | Nagpur (M Corp.) | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| SDPL Greens Rowhouse IIP50500045716 | Wanjara | Certificate Signed | 28 Feb 2027 | 28 Jun 2027 | +4 mo |
| SDPL OmP50500046033 | Nagpur (M Corp.) | Certificate Signed | 31 May 2027 | 30 Sep 2027 | +4 mo |
| Aaranyam - A Project by SDPLP50500049338 | Lavha | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Swapna-Niketan by NMCP50500050570 | Wanjara | Certificate Signed | 31 Mar 2025 | 30 Mar 2026 | +12 mo |
| SDPL Aashray BeltarodiP50500053748 | Beltarodi | Certificate Signed | 30 Sep 2028 | 30 Jan 2029 | +4 mo |
| SDPL Om TatsatP50500055135 | Nagpur (M Corp.) | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
| Suvarnabhumi - A Project by SDPLP50900077789 | Chincholi Bk | Certificate Signed | 31 Dec 2034 | 30 Apr 2035 | +4 mo |
| Aaranyam Wanjara - A Project by SDPLP50500080712 | Nagpur (M Corp.) | Certificate Signed | 30 Apr 2030 | 30 Aug 2030 | +4 mo |
| SDPL SuvarnabhumiPP1190002501173 | Gondkhairi | Certificate Signed | 30 Sep 2032 | 30 Jan 2033 | +4 mo |
| Swapnapurtee - A Project by NMCPM1190002602047 | Nari | Certificate Signed | 31 Jul 2030 | 31 Jul 2030 | On date |
| SDPL Om ShubhlaxmiPR1190002602174 | Mouza Chikhli Deo | Certificate Signed | 31 Dec 2032 | 31 Dec 2032 | On date |
Show all 28 registrationsShow fewer
Sandeep Dwellers Pvt. Ltd, in questions
Does Sandeep Dwellers Pvt. Ltd finish projects on time?
Of 14 MahaRERA registrations whose promised completion date has arrived, 11 kept it (79%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sandeep Dwellers Pvt. Ltd registered with MahaRERA?
22 projects under 28 MahaRERA registrations; 13 completed on MahaRERA.
Does Sandeep Dwellers Pvt. Ltd have MahaRERA regulatory cases?
2 regulatory cases name its registrations.