Deedo IDDD-VTPWNone of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Samata HeightsPM1330002600726 | Bhiwandi (M Corp.) | Certificate Signed | 31 May 2030 | 30 Sep 2030 | +4 mo |
Samata Co Op Housing Society Ltd, in questions
Does Samata Co Op Housing Society Ltd finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Samata Co Op Housing Society Ltd registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Samata Co Op Housing Society Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.