Samarth Tsquare

Deedo IDDD-NB6G

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Samarth Nandadeep HeightsP51800055185PahadigoregaonCertificate Signed31 Oct 202628 Feb 2027+4 mo

Samarth Tsquare, in questions

Does Samarth Tsquare finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Samarth Tsquare registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Samarth Tsquare have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology