Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 29 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay29 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
DeregisteredMajestic MeadowsDeregistered: Majestic Meadows Phase IiNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Majestic MeadowsP99000001734DhekaleCertificate Signed29 Dec 202431 May 2025+23 mo*
Majestic MeadowsP99000016265DhekaleCertificate Signed30 Dec 202330 Dec 2023+35 mo*

Sairaj Nirmaan Realtors, in questions

Does Sairaj Nirmaan Realtors finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sairaj Nirmaan Realtors registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Sairaj Nirmaan Realtors have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology