Sairaj Construction
Deedo IDDD-GF19Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Datta Chhaya Co Op Hou Soc LtdP51700032377 | Badlapur | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| Om Guru Krupa Co-Op. Housing Society LtdP51700056339 | Badlapur | Active | 31 Mar 2027 | — | On date |
Sairaj Construction, in questions
Does Sairaj Construction finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sairaj Construction registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sairaj Construction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.