Company or firm · first RERA registration 2017

Sairaj Builders And Developers

Deedo IDDD-N7Z0

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sairaj Sky Court ApartmentsP51600007109NashikCompleted30 Jun 201830 Jun 2019+12 mo
Sairaj Nexus ApartmentP51600027745AanandwaliCertificate Signed30 Dec 202331 Mar 2024+3 mo
Sairaj Sky Pavilion ApartmentP51600052447MakhmalabadCertificate Signed31 Dec 202730 Apr 2028+4 mo

Sairaj Builders And Developers, in questions

Does Sairaj Builders And Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sairaj Builders And Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Sairaj Builders And Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology