Company or firm · first RERA registration 2017

Saieshwar Projectss

Deedo IDDD-VZ30

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay42 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai EmraldP52100006251Pune (M Corp.)Certificate Signed31 Dec 201831 Dec 2023+60 mo
Sai SquareP52100006310Pune (M Corp.)Certificate Signed30 Dec 202430 Dec 2024+23 mo*

Saieshwar Projectss, in questions

Does Saieshwar Projectss finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.

How many projects has Saieshwar Projectss registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Saieshwar Projectss have MahaRERA regulatory cases?

1 regulatory case name its registrations.