Deedo IDDD-4FWVNone of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai Nagri 16PP1190002502360 | Nagpur (Rural) | Certificate Signed | 31 Jan 2031 | 31 May 2031 | +4 mo |
Saidham Builders & ASA developers, in questions
Does Saidham Builders & ASA developers finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Saidham Builders & ASA developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Saidham Builders & ASA developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.