Sai Shraddha Developers
Deedo IDDD-69KMOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 34 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai IconP51700020449 | Ambivali Tarf Chon | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
Sai Shraddha Developers, in questions
Does Sai Shraddha Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 34 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sai Shraddha Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Sai Shraddha Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.