Sai Rydam Realtors Pvt Ltd

Deedo IDDD-1Y5N

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 72 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay72 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mldc Yashwant Orchid Phase IP99000019485VasaiCertificate Signed30 Dec 202430 Dec 2030+72 mo

Sai Rydam Realtors Pvt Ltd, in questions

Does Sai Rydam Realtors Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 72 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sai Rydam Realtors Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Sai Rydam Realtors Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology