Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 46 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay46 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai SagarP52000006739UlaweCertificate Signed31 Dec 201831 Dec 2018On date
Sai PlazaP52000024625UlaweCertificate Signed30 Dec 202230 Dec 2022+46 mo*

Sai Infra, in questions

Does Sai Infra finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 46 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sai Infra registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Sai Infra have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology