Sai Infra
Deedo IDDD-SVNVOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 46 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai SagarP52000006739 | Ulawe | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Sai PlazaP52000024625 | Ulawe | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +46 mo* |
Sai Infra, in questions
Does Sai Infra finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 46 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sai Infra registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sai Infra have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.