Sai Chaitanya Riverdale Llp
Deedo IDDD-B84ROf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 17 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai Chaitanya RiverdaleP52100077324 | Dudulgaon | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
| Sai Chaitanya RiverdaleP52100077363 | Dudulgaon | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
Sai Chaitanya Riverdale Llp, in questions
Does Sai Chaitanya Riverdale Llp finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sai Chaitanya Riverdale Llp registered with MahaRERA?
1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sai Chaitanya Riverdale Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.