Sahara Builders

Deedo IDDD-BGC8

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record15registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sahara EmeraldP52100033675FursungiCertificate Signed25 Dec 202425 Dec 2024On date

Sahara Builders, in questions

Does Sahara Builders finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Sahara Builders registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Sahara Builders have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology