Deedo IDDD-8DGFOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| GlorisP51800001984 | Borivali | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Gloris ResidencyP51800003895 | Borivali | Certificate Signed | 30 May 2018 | 30 May 2018 | On date |
Sahakar Developers, in questions
Does Sahakar Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sahakar Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Sahakar Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.