Sahakar Developers

Deedo IDDD-8DGF

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
GlorisP51800001984BorivaliCertificate Signed31 Dec 201831 Dec 2019+12 mo
Gloris ResidencyP51800003895BorivaliCertificate Signed30 May 201830 May 2018On date

Sahakar Developers, in questions

Does Sahakar Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sahakar Developers registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Sahakar Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology