Deedo IDDD-4TK3Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 20 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pramukh SadanP51700000743 | Ambarnath(M Cl) | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Patels Prayosha - Pramukh SadanP51700016919 | Ambarnath(M Cl) | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +35 mo* |
| Patels PristinePM1330002501297 | Ambarnath(M Cl) | Certificate Signed | 30 Jun 2031 | 30 Oct 2031 | +4 mo |
Sahajanand Developers, in questions
Does Sahajanand Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sahajanand Developers registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Sahajanand Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.