Sagar Kaluram Patole
Deedo IDDD-ZYZ2Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 10 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Malhar Srushti HomesP52100030222 | Rajgurunagar (Ct) | Certificate Signed | 15 Jul 2025 | 15 Jul 2025 | +16 mo* |
| 7 Sagar PlazaP52100050536 | Rajgurunagar (Ct) | Certificate Signed | 31 Aug 2026 | 31 Dec 2026 | +4 mo |
Sagar Kaluram Patole, in questions
Does Sagar Kaluram Patole finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 10 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sagar Kaluram Patole registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sagar Kaluram Patole have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.