S S Landmark Pvt. Ltd

Deedo IDDD-0AAR

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 35 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay35 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Landmark DivineP51800025174BorivaliCertificate Signed30 Dec 202330 Dec 2023+35 mo*
Meghalok HeightsP51800048163BorivaliCertificate Signed31 Dec 202631 Dec 2026On date

S S Landmark Pvt. Ltd, in questions

Does S S Landmark Pvt. Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.

How many projects has S S Landmark Pvt. Ltd registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does S S Landmark Pvt. Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology