Royal Square Developers

Deedo IDDD-VKMG

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 51 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay51 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Royal OrchidP52100027404LonikalbhorCertificate Signed26 Jul 202225 Jul 2023+51 mo*

Royal Square Developers, in questions

Does Royal Square Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 51 mo late. Across Maharashtra, 73% kept their date.

How many projects has Royal Square Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Royal Square Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology