Deedo IDDD-XGT5Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | AlohaRegulatory order: PROJECT NAME:ALOHA (Regulatory Case No. 166 of 2024) dated 13 March 2024. | 13 Mar 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AlohaP52100017895 | Mulshi | Certificate Signed | 30 Dec 2022 | 31 Dec 2024 | +24 mo |
Rohit Builders, in questions
Does Rohit Builders finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rohit Builders registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Rohit Builders have MahaRERA regulatory cases?
1 regulatory case name its registrations.