Rishabraj Balaji Infra
Deedo IDDD-N8C1Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 23 mo late.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Sankeshwar DarshanComplaint CC12600187 | Not on record |
| complaint | Sankeshwar DarshanComplaint CC12600836 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rishabraj DivineP51800023315 | Borivali | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Sankeshwar DarshanP51800024086 | Borivali | Completed | 30 Oct 2023 | — | On date |
| MatruchhayaP51800034195 | Borivali | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
Rishabraj Balaji Infra, in questions
Does Rishabraj Balaji Infra finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rishabraj Balaji Infra registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Rishabraj Balaji Infra have MahaRERA regulatory cases?
2 regulatory cases name its registrations.