Right Channel Construction Pvt Ltd
Deedo IDDD-46MAOf 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Delta HouseP51800003828 | Borivali | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | +5 mo* |
| Aabiel AvenueP51800005950 | Borivali | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
| Tandice69P51800008220 | Andheri | Certificate Signed | 31 Dec 2019 | 31 Dec 2024 | +83 mo* |
| Grishma HeightsP51800012108 | Borivali | Certificate Signed | 31 Dec 2018 | 30 Jun 2022 | +42 mo |
Right Channel Construction Pvt Ltd, in questions
Does Right Channel Construction Pvt Ltd finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Right Channel Construction Pvt Ltd registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Right Channel Construction Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.