Ricardo Constructions Private Limited
Deedo IDDD-V3RYOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 36 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Grand Slam and Game PointP51800005668 | Kurla | Certificate Signed | 30 Dec 2024 | 30 Apr 2028 | +40 mo |
| Ace and MatchpointP51800007641 | Kurla | Certificate Signed | 30 Jun 2028 | 30 Jun 2028 | On date |
| Center CourtP51800012386 | Kurla | Certificate Signed | 30 Dec 2025 | 31 Aug 2028 | +32 mo |
Ricardo Constructions Private Limited, in questions
Does Ricardo Constructions Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 36 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ricardo Constructions Private Limited registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Ricardo Constructions Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.