Skip to content
Company or firm · first RERA registration 2025

Revoluxe Estates LLP

Deedo IDDD-X80Q

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record47registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kohinoor Business Tower-BanerP52100079205BanerCertificate Signed15 Oct 202915 Feb 2030+4 mo

Revoluxe Estates LLP, in questions

Does Revoluxe Estates LLP finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Revoluxe Estates LLP registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Revoluxe Estates LLP have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology