Regency Aawishkar Sarsan Developers Llp
Deedo IDDD-HMBWOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
5 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Regency AstraComplaint CC12500238 | Not on record |
| complaint | Regency AstraComplaint CC12600507 | Not on record |
| complaint | Regency AstraComplaint CC12601252 | Not on record |
| appeal | Regency AstraAppeal AT05/00271/2026 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Regency AstraP52100032177 | Baner | Completed | 30 Nov 2024 | 29 Nov 2025 | +12 mo |
| Regency AstraP52100046664 | Baner | Certificate Signed | 30 Nov 2026 | 30 Mar 2027 | +4 mo |
| Regency Astra Phase IIIP52100053943 | Baner | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Regency Astra Phase IVP52100081020 | Baner | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Regency Astra Phase VPR1260002501708 | Baner | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Regency Aawishkar Sarsan Developers Llp, in questions
Does Regency Aawishkar Sarsan Developers Llp finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Regency Aawishkar Sarsan Developers Llp registered with MahaRERA?
4 projects under 5 MahaRERA registrations; 1 completed on MahaRERA.
Does Regency Aawishkar Sarsan Developers Llp have MahaRERA regulatory cases?
4 regulatory cases name its registrations.