Redwood Builders
Deedo IDDD-MC0POf 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Redwood Paraj GardenP52000032423 | Pen (M Cl) | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Redwood ParadiseP52000079046 | Pen (M Cl) | Certificate Signed | 30 Sep 2028 | 30 Jan 2029 | +4 mo |
Redwood Builders, in questions
Does Redwood Builders finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Redwood Builders registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Redwood Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
