Company or firm · first RERA registration 2017

Raunak Corporation

Deedo IDDD-ZE0J

Of 9 registrations whose promised date has arrived, 8 kept it (89%). The rest ran a median 4 mo late.

Projects1515 RERA registrations
Kept RERA date89%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

5 of 15 registrations with dates moved or missed their RERA date · months late against the original promise

15 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Raunak City Sector IV - D2P51700003210AdharwadiCertificate Signed30 Dec 202530 Dec 2025On date
Raunak City Sector IV - D1P51700003377AdharwadiCertificate Signed30 Dec 202530 Dec 2025On date
Raunak City Sector II - B7P51700006182AdharwadiCertificate Signed31 Dec 201831 Dec 2018On date
Raunak City Sector IV - D10P51700009331AdharwadiCertificate Signed30 Dec 202530 Dec 2025On date
Raunak City Sector IV - D9P51700017488AdharwadiCertificate Signed30 Dec 202730 Dec 2027On date
Raunak City Sector IV - D3P51700019790AdharwadiCertificate Signed30 Dec 202430 Dec 2025+23 mo*
Raunak City Sector IV - D4P51700019962AdharwadiCertificate Signed30 Jun 202530 Jun 2025On date
Raunak City Sector IV - D8P51700020182AdharwadiCertificate Signed30 Dec 202530 Dec 2025On date
Raunak City Sector IV - D5P51700020240AdharwadiCertificate Signed30 Jun 202630 Jun 2026On date
Raunak City Sector IV - D7P51700020241AdharwadiCertificate Signed30 Jun 202630 Jun 2026On date
Raunak City Sector IV - D6P51700020261AdharwadiCertificate Signed30 Dec 202730 Dec 2027On date
Raunak City Sector VI - F2P51700033757AdharwadiCertificate Signed31 Dec 202830 Apr 2029+4 mo
Raunak City Sector VI - F1P51700033762AdharwadiCertificate Signed31 Dec 202830 Apr 2029+4 mo
Raunak City Sector VI - F3P51700033972AdharwadiCertificate Signed31 Dec 202830 Apr 2029+4 mo
Raunak SereneP51700045210Thane (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
Show all 15 registrationsShow fewer

Raunak Corporation, in questions

Does Raunak Corporation finish projects on time?

Of 9 MahaRERA registrations whose promised completion date has arrived, 8 kept it (89%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Raunak Corporation registered with MahaRERA?

15 projects under 15 MahaRERA registrations; 10 completed on MahaRERA.

Does Raunak Corporation have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology