Company or firm · first RERA registration 2017

Ram India Shelters

Deedo IDDD-WTMX

Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 4 mo late.

Projects88 RERA registrations
Kept RERA date80%Maharashtra: 73%
Median delay4 mowhen late
First sales on record58registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 8 registrations with dates moved or missed their RERA date · months late against the original promise

8 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Green Hive B1P52100002453FursungiCertificate Signed31 Dec 201831 Dec 2018On date
Green Hive Plus A13P52100018486FursungiCertificate Signed30 Dec 202230 Dec 2022On date
Green Hive Plus A1P52100018708FursungiCertificate Signed30 Dec 202230 Dec 2022On date
Green Hive Plus Wing A2P52100031108FursungiCertificate Signed31 Dec 202431 Dec 2024On date
Green Hive Plus Wing A3P52100033707FursungiCertificate Signed31 Dec 202531 Dec 2025+11 mo*
Green Hive Plus Wing A4P52100047390FursungiCertificate Signed31 Dec 202630 Apr 2027+4 mo
Green Hive Plus Wing A5P52100080424FursungiCertificate Signed31 Aug 202931 Dec 2029+4 mo
Green Hive Plus Wing A6PR1267072500502FursungiCertificate Signed31 Aug 203031 Dec 2030+4 mo

Ram India Shelters, in questions

Does Ram India Shelters finish projects on time?

Of 5 MahaRERA registrations whose promised completion date has arrived, 4 kept it (80%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Ram India Shelters registered with MahaRERA?

8 projects under 8 MahaRERA registrations; 4 completed on MahaRERA.

Does Ram India Shelters have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology