Rajesh Virendra Gupta

Deedo IDDD-SA1F

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
nest 1 phase 2P52000010177BoriwaliCertificate Signed30 Sep 201830 Sep 2019+12 mo
Nest 2 Phase 2P52000014563T. NeedCertificate Signed30 Sep 201830 Sep 2018On date

Rajesh Virendra Gupta, in questions

Does Rajesh Virendra Gupta finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rajesh Virendra Gupta registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Rajesh Virendra Gupta have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology