Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 55 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay55 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
RadhekrishnaP52100016670LahagaonCertificate Signed30 Mar 202230 Mar 2022+55 mo*

Rajesh Ramchandra Mehta, in questions

Does Rajesh Ramchandra Mehta finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 55 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rajesh Ramchandra Mehta registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Rajesh Ramchandra Mehta have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.