Rajan Namdeo Pore

Deedo IDDD-Y137

Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 4 mo late.

Projects56 RERA registrations
Kept RERA date80%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 6 ran past the RERA date

Months late against the original RERA promise, per registration

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Laxminarayan ArcadeP52700019419Wai (M Cl)Certificate Signed30 Oct 202330 Oct 2023On date
Laxminarayan ArcadeP52700019452Wai (M Cl)Certificate Signed30 Oct 202330 Oct 2023On date
Aditya ViharP52700030810PirwadiCertificate Signed31 Aug 202431 Aug 2024On date
Ojas ViharP52700030815PirwadiCertificate Signed30 Sep 202430 Sep 2024On date
Ballaleshwar Complex-1P52700053330Wai (M Cl)Certificate Signed30 Jun 202630 Jun 2026+4 mo*
Skyview TowersP52700055592Karanje Tarf Satara (Ct)Certificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology